Consider an instruction pipeline having 4 phases with duration 60, 50, 90 and 80ns.
Given latch delay is 10 ns.
Calculate the speed up ratio.
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
FORMULA FOR SPEED OF NON-PIPELINED AND PIPELINED RATIO: Speed Up (S) =Non-pipelined execution time/Pipelined execution time Pipeline Execution Time = Maximum delay due to any stage + Register Delay = Max { 60, 50, 90, 80} + 10 ns = 90 ns + 10 ns = 100 ns Non-pipeline execution time for one instruction = 60 ns + 50 ns +90 ns + 80 ns = 280 ns Speed up = Non-pipeline execution time / Pipeline execution time = 280 ns / 100 ns = 2.8